SAH redevelopment update: Still ahead of schedule

Stage four lockdown in Melbourne has impacted every area of life, including the construction sector. The St Andrew’s Hall redevelopment has been classified as a large scale commercial project. This means that the workforce has been reduced to 25% of full capacity with a maximum of 13 contractors allowed on-site at any time. Two weeks into these restrictions and the project is still tracking two days ahead of schedule. Please keep praying that St Andrew’s Hall project will come in on-time, on-budget and safely.